Portfolio
Industrial2023 · Case Study

Wastewater treatment plant SCADA and motor control

Carson, CA · 25 MGD facility

Upgraded motor controls and instrumentation power for a 25 MGD treatment plant, with soft starters on large pumps and a hardened controls power system tied to standby generation.

Service
480V / 1,200A
Pumps
4 × 150 HP
Soft start
Reduced-voltage
Standby
1 MW diesel
Wastewater treatment plant SCADA and motor control
01Scope of Work

What we were engaged to build.

Two NEMA 3R motor control centers with solid-state soft starters on four 150 HP influent pumps.
Hardened 208/120V controls power bus, UPS-backed for instrumentation and PLCs during outages.
Standby 1 MW diesel generator with open-transition ATS for process ride-through.
Stainless NEMA 4X enclosures and sealing for corrosive and wet environments.
4–20 mA instrumentation loops and MODBUS RTU links back to the plant SCADA.
NEC 430 motor circuit protection, 645 IT equipment and 700 life-safety compliance.
02Technical Specifications

Actual ratings, devices and standards.

The service voltages, equipment ratings, protective functions and codes this project was built and tested against.

Service
480/277V, 3Ø, 1,200A main
MCCs
2× NEMA 3R, 600A each
Soft starters
4× 150 HP solid-state, 350% ISC
Controls power
208/120V, 100A, UPS-backed
Standby gen
1 MW diesel, 480V, open-transition ATS
Instrumentation
4–20 mA, MODBUS RTU to SCADA
Environment
NEMA 4X enclosures, stainless
Standards
NEC 430, 645, 700
03Solutions Deployed

The specific electrical solutions we used.

How each design decision solved a real constraint on this project — from redundancy and coordination to protection and commissioning.

01

Solid-state soft starters on large pumps

Ramping the 150 HP pumps over 15 seconds cut inrush from 600% to 350%, protecting the generator and stopping the voltage sag that used to drop PLCs on every start.

02

UPS-backed controls power bus

A dedicated 208/120V controls bus on a small UPS keeps PLCs, instruments and SCADA alive through a generator transfer, so the plant never loses visibility during an outage.

03

NEMA 4X stainless for corrosive zones

Enclosures near the aeration basins are 316 stainless NEMA 4X with sealing gaskets and stainless conduit, surviving the H2S and moisture that ate the old painted steel.

04

4–20 mA + MODBUS RTU to SCADA

Every loop is a 4–20 mA signal with a live-zero fault indication, and the MCCs report breaker status over MODBUS RTU, so a failed instrument reads as a fault instead of a false normal.

04On Site

From the build.

Wastewater treatment plant SCADA and motor control — view 1
Wastewater treatment plant SCADA and motor control — view 2
Wastewater treatment plant SCADA and motor control — view 3